CompanyTrenz Electronic GmbH
PCN NumberPCN-2020327
TitleTE0808-03 04 to TE0808-04 05 Hardware Revision Change
SubjectHardware Revision Change
Issue Date

JJJJMMDD2020-04-08

Products Affected

This change affects all Trenz Electronic TE0808 SoMs of revsion 0304: TE0808-04-03*.

Revision 04 is still continued. See Production Shipment Schedule below for further details.

Affected Product

Replacement
TE0808-04-*TE0808-05-*

Changes

#1 Revised PL_VCCINT power supply.

Type: PCB change

Reason:  Improve design for higher core utilization.

Impact: Up to 30A 30 A PL core current availablepossible.

#2 Added signal BG1, revised routing and placement of DDR4

Type: Schematic change

Reason: Add support of new packages of DDP DDR4 ICs.

Impact: DDP DDR4 now supporteted. Assembling four 32Gb DDDP DDR4 packages a maximum of 16GB RAM is now supported.

#3 R5 value changed to 49.9 Ohm and connected to VCCO

Type: Schematic change

Reason: Xilinx recommondation UG583.

Impact: R5 pulled up to VCCO_PSDDR.

#4 Added test points

Type: Schematic change

Reason: Improve factory testability.

Impact: Atomatic Automatic testing possible.

#5 Added MAC EEPROM U4 and

...

I2C pullups

Type: Schematic change

Reason:  Improve interchangeability with TE0803 series.

Impact: User EEPROM accesible via I2C bus PLL_SCL/SDA. Added pull up resistor to I2C busPLL I2C bus.

#6 Revised FPGA location

Type: PCB change

Reason: Improve Layout and support for small BGA cooler with BGA frame clips.

Impact: Package placed 1.5mm closer to connector J3.


Note: Due to the changes above the height profile of the module is changed. Using TE0808-05 board as a replacement or in system designed for TE0808-04, review and adaption of mechanics e.g. cooling solutions have to done.

Method of Identification

The revision number is printed in the top side of the PCB.

draw.io Diagram
bordertrue
diagramNameRN_TE0808
simpleViewerfalse
width200
linksauto
tbstyletop
lboxtrue
diagramWidth138
revision1

Production Shipment Schedule

From XXXXX, after old stock is gone. If the new revision is not suitable for your application and still the former revision of the board is needed, please contact us.The new revison 05 is available from Juli 2020. Revision 04 is still continued. For new designs revison 05 should be used. It is recommended to switch to the new revision when possible. 


Contact Information

If you have any questions related to this PCN, please contact Trenz Electronics Technical Support at

Disclaimer

Any projected dates in this PCN are based on the most current product information at the time this PCN is being issued, but they may change due to unforeseen circumstances.  For the latest schedule and any other information, please contact your local Trenz Electronic sales office, technical support or local distributor.

...